Hi!
I have a weird behavior in one of my workflows.
The workflow is simple: Todo->In progress<->In review->Done
As you can see a task can be moved back from In review to In progress.
When a user changes the status from In review to In progress, the assignee is automatically updated with the current user.
Reviewing the History I've found that it was done by Automation for Jira, I don't have any Automation enabled and the workflow's post functions is as follows:
Any ideas?
Thanks!
Hi @Daniel Lopez,
Have you checked both project and global automations? The easiest way to understand which automation assigns the issue is to transition an issue from In review to In progress and then check the global automation audit log:
Hope this helps,
- Manon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.