When I export an issue list to Excel in the "Original Estimate" column I get 28800 for 8 hours. Any way to easily format the content into something useful? Thanks

3 answers

1 accepted

1 vote
Answer accepted
Renjith Pillai
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 15, 2013

Add a new scripted field that converts the Original Estimate to whatever type of representation you want and use that in the Excel export

https://jamieechlin.atlassian.net/wiki/display/GRV

0 votes
Natalie Hobson
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 14, 2013

What about adding a formula to the excel document so it converts the value from seconds to hours?

0 votes
Jeison
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 14, 2013

Hi Anne,

That value is in seconds.

Cheers,

Anne Jane Gray
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 14, 2013

Sorry I did not see this! Thanks that helps.