I want to add an additional board/project in Scenario b of my portfolio planning. How can I do that? Reason: I want to separate specific projekt workload from Feature requests and want to show the impact of feature Requests
Thanks in advance
This is not possible - Scenarios are fixed to the plan as you have it configured to boards/projects.
One way to accomplish what you're describing: include the feature requests in your board configuration. Then, associate these workload impacting feature requests to a unique Epic called "Pending Feature Requests" (so they're not at the bottom of the plan) and leave them unestimated and not assigned. Then, in Scenario B you can put estimates on them and see the impact to your schedule and workload.
-Jason Golden
Denver AUG Leader
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.