Hi,
I can't get setup to show external sprints on the timeline.
I'd like to
I'm interested in showing External Sprints on the timeline that is described in the documentation.
screenshot form documentation.
I'd appreciate an answer or tip on how can I realize this need and if that's a configuration issue or bug or outdated documentation.
Advanced Roadmaps for Jira v9.4.3 Data Center
thanks
Michal
For what I've read. It seems that using the Project or Filter issue source will only retrieve the existing value of the sprints and mark them as EXT.
But if you'd like to use sprints in Plans and change their values on the timeline view, you'll need to import the board.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.