Advanced roadmap not reflecting updated original estimates

Rasmus Höglund
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 2, 2025

Hi!

I updated the "Original estimate" for a story from 6 to 8 to 15 hours via the work item view. The changes were made a few hours/days apart.

In the Advanced Roadmap, the "Estimates (h)" column still says 6 hours. I have no pending changes to save in the roadmap.

Is there a way to "recalculate" the original estimates, or is this a bug?

 

Untitled.pngUntitled.png

1 answer

1 accepted

1 vote
Answer accepted
Rasmus Höglund
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 2, 2025

Found the problem. The "Estimates (h)" column in the roadmap does not show the original estimate. It shows the remaining estimate.

So, when updating the original estimate in a work item, I must also remember to update the "Time remaining". 

Screenshot 2025-06-02 155054.png