Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Auto-scheduler does not take into account the number of team members

Wojciech Skrzypczyk
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 3, 2025

I have a problem with Auto-Scheduler functionality.

Unfortunately, I cannot manage to set the schedule correctly and no matter how I change the options, the auto scheduler does not want to set two items together simultaneously.

I have configured teams (for testing purposes I have selected a team of 2 people whose shared resources are 80h per week). 
image (7).png

In addition, my plan is set to one that estimates tasks in days.image (6).png

I select four tasks, assigned only to the team of these two people.

The tasks are appropriately marked and pinned to each other. They have filled in estimate times (10 days, 10 days, 4 days, 4 days).  set by me manually)

image (10).png

And the auto scheduler loses Original Time Estimates and simultaneously work options.

image (9).png


Is something wrong with my settings? What should I do to make sure that the auto scheduler feature will distribute the work simultaneously?

This is just a test, the task that awaits me concerns a larger number of teams, dependencies and tasks and in order to complete it, it would be very useful for me to be able to use the option of automatic time setting adjusted to the resources at our disposal.

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events