Hi,
I have an item A which has end date of 10/03 and has an outgoing dependency to item B which I manually assigned 11/03 as the start date. Is there a way to make it so if I decide to move the end date of item B to say 15/03, then item B will automatically change it's start date to reflect the change made to item A?
In simpler words, I want everything to shift right in case of scope creep. At the moment the only way I can do it is manually
I succeeded using the following thread - however it is not intuitive at first sight, Advanced Roadmaps heavily relies on the "Original Estimate". The Due Date then is set according to the issue which it is blocked by.
Cheers,
Daniel