I see you can define releases based on estimations and team(s) based velocity. does the portfolio plugin use similar values/calculations for uncertainty like the 'Version Report' plugin?
That plugin uses average velocity and uses that to estimate a predicted, optimistic and pessimistic completion date.
Hi @Jasper Saaltink,
Portfolio is currently looking at the velocity, estimations, priority and, potentially, skills and stages. There is currently no uncertainty mechanism baked in the Portfolio algorithm.
Portfolio does offer the ability to have multiple scenarios that you can use for best/worst case planning which could achieve your goals.
I'd be interested to hear more about your use case as we're interested in bringing smarts and insights in Portfolio to the next level while making it easier to use!
Cheers,
Thomas
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.