I'm currently planning Epics in Portfolio.
We've estimated an epic to take 15 days
When Portfolio automatically schedules it sets the start / end date to be Nov 8/ Nov 19.
I expected the scheduler to slot 3 weeks of time. Nov 8 -> Nov 29 (as it doesn't include weekends)
I believe that it's assigning 11 days because it's assignign two people to work on it. How can I set it up so that automatically, only one person is assigned to an epic?
Hi @Vincent Huang,
This is currently not supported, I've created a feature suggestion here: https://jira.atlassian.com/browse/JPOSERVER-2034
I'd encourage you to vote and explain your use case on it in the comments!
As a workaround, you would currently have to manually assign the epic to a single team member.
Cheers,
The Portfolio for Jira Team
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.