I have 3 Epics with the following names:
I would have expect the start date for Epic 2 to become the end date of Epic 1
This does not happen.
How do you make it work?
Or do you just have to manually enter start dates the align with the dependency?
-Alan
Hi @Alan Bell and welcome to the community!
In case of dependencies with a planning conflict, a decision needs to be made. Either you try to complete Epic 1 earlier, or you delay Epic 2 (or you think of a clever alternative to eliminate the dependency).
Jira doesn't make that decision for you. Which I personally appreciate a lot. Many factors can come i to play making such a decision. Maybe different teams are responsible for Epic 1 and Epic 2: in that case a dialogue needs to take place.
Advanced roadmaps helps to identify and track planning conflicts; bit it doesn't step in.
Kind regards Rik
I agree with Rik :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I agree with you in general but if I make a dependency I would expect it to honor that.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Probably, try Jira automation ..1) using the link relation to pickup date 2) update epic start date..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.