Dear Team,
We have started using Scrum capacity planning/ mgt. using “Plans”. This is very useful in viewing capacity planning for teams in a program.
But we are struggling to visualize capacity allocation & utilization for Kanban.
Kindly help.
Regards,
Vishal
Hi @Vishal Kochhar Capacity for Kanban teams is very limited in Plans.
First of all, Kanban teams can only use time-based estimates.
For Kanban teams, work is broken down into iterations which each last one week. You can set the weekly capacity of a Kanban team in either days or hours, but the length of the iteration cannot be changed.
The capacity of a Kanban team can only be measured in total hours/week for the entire team. There are no features regarding holiday schedules or workload schedules.
Personally, this is a huge pitfall/gap when using Plans in Jira Premium.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, I tried for all available views in Plans but not able to visualize.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.