Hi everyone, I am using Jira advanced roadmaps and created "plans" including initiatives and epics. So far so good.
Next step was to add a "program", so that I can aggregate different plans. In the configuration of the "program" I added my plans.
Problem: when I select "hierarchy level = epic" on the program dashboard, everything works as expected (diagram shows epics with some bars on timeline). But not, if I select "hierarchy level = initiatives". Nothing is shown ("for this hierarchy no initiatives are planned"), even though I created some initiatives for my plans/program (with start/end dates). I also synchronized / refreshed plans/programs.
Thanks for any tips / advice
found it out myself - after another "synchronize" on the "tab = scope" my initiatives are now shown on the dashboard für "program".
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.