Hi, community! I'm new here and thought that you could give me some advice.
I'm struggling to create a multi-project roadmap. I want to plan by people and features. Currently, I've found only the way to do that in excel. I would appreciate it if you could share how you build the roadmaps in Jira for more than 1 project.
Thanks in advance! Have a nice day!
Once you create your program and plan in JIRA Roadmap , you should be able to view issues from multiple project.
On the configuration screen , you can add remove - boards projects etc you want to add in your roadmap plan view.
Fields in jira issuetypes also play a role - epic links should be populated , parent links should be populated so that you get a good hierarchy view in roadmap plan.
But yes , filter and project/s as source should help you get data from multiple projects.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.