After creating the plan, different stories and epics taken concurrently. I want that to be changed in a way once story A is complete Story b can be taken.
Example:
Story A (100 story points) and Story B (100 story points)
Team velocity: 100
portfolio schedule showed like : Sprint 1 - Story A and B (each 50 points burned)
Sprint 2: both stories are done.
Expected: Sprint 1: Story A complete and Sprint 2: Story B complete
Can you please help on how to change the settings to incorporate this?
Hello Mohamed,
It sounds like Story B has been manually added to the same sprint that Story A is part of. And when Manual association is in place this overrides the calculation performed by portfolio.
Check out the Scheduling Behavior Documentation for more details on this.
-Earl
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.