In the dropdown selection for Issue Sources withing my Portfolio, all my business projects/boards do not appear. They are essentially Kanban boards, so why is this the case?
Hey @Vivian Tang! I just tested in one of our demo instances and was able to add a Jira Core (Business) project as an issue source to a Portfolio Plan.
(JIRA v7.3.1 / Portfolio for Jira v2.15.0)
Try adding the project itself rather than the board. This should have the same results as you wouldn't be sprinting in a Jira Core project anyway.
Hope this helps!
Hi, this has resolved the issue but can you please let me know why a business project board is not a board?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.