Hello all,
I have a question regarding the auto-schedule criteria. I have a Sprint of 2 weeks time and team velocity of 55 story point/ Sprint.
In this plan, there is only 1 story with highest priority, however, in the auto-schedule result, it is not planned in the first Sprint.
I have also try the ranking, but seems it is not related either.
Does anyone know the logic of it? Thanks. uto-schedule? Thanks.
If you change the hierarchy filter to just show stories - what does the ranking look like?
Stories and epics are ranked independently (every issue in Jira has a global unique rank) and a story can be ranked higher than another story belonging to the a high ranked epic.
The priority field is not considered by the auto-scheduling algorithm, but the rank is.
Regards,
Dave
Check if there is a dependency on story or it is assigned to a release in future.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.