I have created a new portfolio plan. Unfortunately user stories which are already in status Done are not included in the plan. Thus any progress on epic level is incorrect.
Is there a way to include completed stories in a portfolio plan?
Your stories are (likely) included in your plan, you just need to make them visible.
This is assuming your issue source is a board or filter based on something simple like:
project = ABC ORDER BY Rank ASC
Here are a few of things to consider:
See https://confluence.atlassian.com/jiraportfoliocloud/tracking-progress-and-status-828785247.html for more information.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It's on cloud.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The current cloud instance of Portfolio will only include open issues. The inclusion of closed issues has been logged as a suggestion in Atlassian's Jira: https://jira.atlassian.com/browse/JPOCLOUD-1267
Hope this helps!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.