In the old user interface I am able to set a conversion rate for story points to hours per data source. This we need because we are using a company wide portfolio plan that includes multiple teams with each their own agreement on what a story point is worth and some teams that do not work with story points but hours.
Since the new UI has been released, this feature is missing which prevents me from switching to the new approach and make use of all the new improvements.
If you will not bring this feature back, should I be using Portfolio differently (e.g. a different Plan per team and a Program to get the entire overview?). I think this won't work for us as there are interdependencies in between teams but any suggestion is very welcome.
I don't think you will see this coming back - story points are not hours. They're not any simple multiplier of hours. I've seen 1SP take two days and 8SPs take 30 minutes. Their relative complexities were right, the length of time to close them was very very different.
Ok fair answer as that is generally the case anywhere, especially with each team having their 'standards' for assigning story points to certain tasks. We were trying to create a company wide portfolio (Business + IT departments) but maybe this is too ambitious :)
Question I have then is:
How will a portfolio plan with multiple teams work then if each team has their own way of story pointing? I assume each team will have to work with SP's and a (scrum) board as an issue source so that the velocity from each team is used to determine how long each 'bar' should be in the plan schedule?
E.g. if we have an issue with 10SPs and a team 1 and a team 2. Team 1 has double the velocity of team 2. If this issue is reassigned from team 1 to team 2, I would expect that the visualised bar (with start, end and duration) will also become twice as long whilst still having the same amount of story points?
Trying to figure out how this will work in practice so any help is very welcome!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If your teams are estimating separately then wouldn't it stand to reason that upon reassignment the new team would estimate the work for inclusion in your plan? also comparing velocity across teams is dangerous. Velocity is a team-centric planning tool. You can't plan how long it will take a team to complete work based on another team's estimate and velocity.... I think you are going to find many gaps with the way you are configuring this...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.