Hi All,
I am new to JIRA portfolio and am trying to schedule a "Project" . I am just interested in tracking at a high Level(Milestone Based planning) in Days.
I have created a few tasks under the Epic and have set dependencies. The first task's duration is 40 days but I am noticing that the "schedule end date" is not changing .
Observed behavior:
Task 1 - Estimate = 40 days, Sch. Start = 08/20/18, Sch End = 08/28/18
Expected Behavior :
Task 1 - Estimate = 40 days, Sch. Start = 08/20/18, Sch End = 10/20/18
Appreciate any insights/clues on this behavior.
One possibility here is that the default team working hours is being used to calculate a date indicating that the task can be completed in less time.
So for example your task might take 40 "person-days" but the default team capacity 200 weekly hours (e.g. 25 person days per sprint). One thing you could try is changing the team capacity to be a 40 hour week (you can achieve this by assigning a person to the team).
Regards,
The Portfolio Team
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.