I've got a portfolio plan defined with teams that have the necessary skills and estimates. Yet, the scheduler is displaying an "availability violation". Has anyone else experienced this? Have any thoughts on things I could try to resolve it?
I figured this issue out. I had required skills split across teams. Portfolio won't allow multiple teams to be assigned at the story level. Once I put all the people/skills in one team, the availability violation was resolved.
Now if I could just figure out why Portfolio thinks there are skill gaps to complete a story.