Hi
I'm getting this error on some of the issues that are included in our portfolio plan.
"Item ignored. The item is assigned to an invalid sprint."
I have one project with three board, one team per board, paralelle sprints is diabled . (Is this not recommend?) All board are included into portfolio. Some of the issue have this error message. Did I do something wrong?
Hi Mikkel,
It looks like you might be experiencing the same issue described in this threads:
At the time of answering those questions we didn't have support for parallel sprints but we do now. I would definitely recommend enabling parallel sprints as this might resolve your issue.
I hope this helps,
Regards,
Dave
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.