Hi.
How is the burndown guideline calculated in greenhopper's reports?
I can't see a place for entering expected burndown hours pr day...
Thank you.
Morten.
Solved! Go to Solution.
You do need to make sure that you've got estimates for all your tasks before starting the Sprint. I made the mistake of starting a Sprint before everything was estimated, and couldn't work out why the guideline was invisible. Of course, it was going from 0 to 0!
true. though, you could also base the estimation on the number of issues (must be configured in Board configuration).
Another issue to watch out for is the burndown will NOT remove weekends and Holidays even if you tell it not to account for them....this totally throws off the burndown line. Unless you work 7 days a week 365 days a year then you're okay ;-)
To those still interested: it's possible to modify the non-working days in the Burndown Chart, as of Greenhopper 6.1.1.
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Apply agile practices
Transform how you manage your work with agile practices, including kanban and scrum frameworks.
Learning Path
Configure agile boards for Jira projects
Learn how to create and configure agile Jira boards so you can plan, prioritize, and estimate upcoming work.
Jira Essentials with Agile Mindset
Suitable for beginners, this live instructor-led full-day course will set up your whole team to understand how to use Jira with an agile methodology.