Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Estimating stories and tasks in the sprint.

G Krithica
Contributor
March 25, 2019

Hi,

I have set of stories in sprint and tasks that are linked to stories not sub-tasks.

I use story points for estimates.

Now in the burn down chart it shows task and stories separately.

Is it possible like story 1- have 4 linked tasks.

Like 10 story points for Story 1 split up based on complexity to linked tasks.

Like Task 1 - have 2

task 2 have 3

task 3 - 4

task 4 have 1 story point so the sum up should be equal to story point of story?

And if 1 task is completed the story point should be burn down for both task and story.

Please let me know if this is possible and how to do it?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Scott Theus
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 4, 2019

Hi @G Krithica ,

Unfortunately, no...I am not aware of any way to do this in Jira. "Task" and "Story" issue types are at the same level, hierarchically; meaning the breakdown for issue types is Epic ---> Story, Task, etc. ---> Subtask. There are only three levels, and Epic is at the top while Sub-tasks is at the bottom. 

The reasoning for having Tasks different from Sub-tasks and on the same level as Stories relates to the value the issues provide to the project. A Story is work that adds value, a Task is work that needs done but does not ad value, and a Sub-task is a piece of work within a Story or Task. 

If you use Portfolio you may be able to have them roll up to an Initiative and burn down from there, but I've never tried it. 

-Scott

TAGS
AUG Leaders

Atlassian Community Events