Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

WBS Gantt Chart for JIRA - re create the issues

Nisan Lati July 31, 2024

Hello,

i build nice plan in , WBS Gantt Chart for JIRA

than i export it to MS project. there i do some adjustments.

now i want to import this plan again to jira - to WBS Gantt...

the problem is that all issues are created again...

i want to update the plan not to recreate it... (now i have all issues duplicated)

 

Is there limitation i miss? workaround?

 

thanks

 

1 answer

Suggest an answer

Log in or Sign up to answer
1 vote
Charlotte Santos
Contributor
July 31, 2024

Hi @Nisan Lati

Thank you for posting! I’m Charlotte from WBS Gantt-chart support team.

That's the expected behavior of the app, when you import the .mpp file, WBS will create the issues in the project you selected. So far, there is no way to just import updates. You need to do the adjustment manually in WBS Gantt Chart.

This should clarify things out for you, however don't hesitate to share your doubts or questions about the app, we'll be happy to help you! 😉

All the best, 

Charlotte S. | Support Engineer
Ricksoft Support Team

 

TAGS
AUG Leaders

Atlassian Community Events