How to create a story burnup (total created and total resolved) by week

Broussard_ Anna April 30, 2025

I am able to create a story burnup with 2 series, total created and total resolved by week. I don't really care about sprints, but rather I want to see total for my project over a time range. My chart is based on story created date, so even if the story was created in week 1, and story point was added in week 3, my chart will show the increase in week1. How do I get a burnup based on when the story points were added?  

1 answer

0 votes
Danut M _StonikByte_
Atlassian Partner
May 1, 2025

Hi @Broussard_ Anna,

I am not very familiar with the Analytics, but could eventually try using a cumulative chart or stacked Areas, by Story Points. 

If you don't manage to figure it out in Analytics, you could look for Jira apps on Atlassian Marketplace that provides this type of chart. 

If you consider the idea of using an app, this can be easily achieved by using some of the gadgets offered by our Great Gadgets app. 

Release Burndown Burnup Chart gadget - lets you generate the burnup. All you have to do is to configure it with a filter/JQL that returns your issues, calculate by SPs, set the timeline and group data by 1 week. 

image.png

Cumulative Flow Diagram gadget - lets you generate a cumulative stack area chart based on the story points of the issues from filter/JQL, grouped weekly and split by status category.

image.png

Danut.

 