Hi,
I'm new to bamboo.
I have configured a single plan with 3 different stages where second 2 stages are manual stage.
When I'm trying to rerun the particular stage say stage 3, it requires to run previous stage say stage 2 also.
Seems I'm facing this case only in after successful run of stage 3.
When failure of stage 3 , I can able to rerun stage 3 alone.
but I need to rerun stage 3 alone after successful run too
Can anyone help me on this?
It is not possible. You can check https://jira.atlassian.com/browse/BAM-9611 for some context. Also, check the last comment about deployment projects.