What's the step-by-step process for upgrading from Server to Data Center in cluster mode?
According to the docs, I just need to apply the new Data Center license to our current server. But is that it? Shouldn't I also run the Data Center installer?
Hi @Miba
Pasting the DC license into an existing server license will "upgrade" from server to data center.
Of course it will not enable a clustered mode with an extra node. For that you need to install an extra Bitbucket node indeed. And there are other things to keep in mind too like a separate elastic search instance, load balancer, shared file system etc.
More info about setting up a clustered instance can be found here.