Hi ,

 

I have created tasks in multiple pages and assigned them to others users, is there a way to track the status of all the tasks at one place like in a page or dashboard using a Macro or query.

we are using confluence version 4.3.2.

 

Thanks in advance.

Pavan

 

1 answer

0 votes
rrudnicki
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 21, 2015

Hi Pavan, 

 

I believe you can do this using the Task Report Macro. You have the Task Status option which show complete or incomplete tasks. 

 

On this documentation you can find more details and some examples:

https://confluence.atlassian.com/display/DOC/Task+Report+Macro

 

Regards, 

Renato Rudnicki