Can the chart plugin for Confluence create Gantt Charts?
Yes it does. However, it looks like the documentation page that use to exist is not publicly available anymore. It is not clear that part of the chart plugin has been maintained completely as one of the old examples does not work. At some point, this will all be corrected.
Here is a simple example that works - use insert wiki markup:
{chart:type=gantt|dataOrientation=vertical|columns=,,1,2,3,4|displayData=before|width=500|dateFormat=MM/dd/yyyy}
{csv:output=wiki}
Plan, Start, End, Percent\\complete
Create issue, 1/30/2007, 2/1/2007, 30%
Provide examples, 1/30/2007, 2/7/2007, 40%
Write code/tests, 2/3/2007, 2/4/2007
Write docs, 2/4/2007, 2/5/2007
Release update, 2/5/2007, 2/5/2007
{csv}
{csv:output=wiki}
Actual, Start, End, Percent\\complete
Create issue, 1/30/2007, 2/11/2007, 100%
Provide examples, 1/30/2007, 2/17/2007, 90%
Write code/tests, 2/3/2007, 2/14/2007
Write docs, 2/4/2007, 2/15/2007
Release update, 2/5/2007, 2/15/2007
{csv}
{chart}
Another quick question, would it be possible to create a chart without having a built in project plan? Say, if I wanted to use a third party software to create my own project plan, could I then use the Chart plugin to display that project plan as a Gantt Chart?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, only if you could get the software to create a table (csv like above) or similar that the gantt chart type needs to create a chart.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi - I have plotted the gantt chart. Would want to also display the value labels for each bar i.e. start and finish dates in example....unable to find out such attribute.
{chart:type=gantt|xLabel=Projects|yLabel=Planned Dates|legend=false|timeSeries=true|timePeriod =month|dataOrientation=vertical|columns=,,1,2,3,4,5|rangeAxisLowerBound=11/01/2013|rangeAxisUpperBound=12/31/2014|displayData=false|width=1000|dateFormat=MM/dd/yyyy}
{excerpt-include:Consolidation Server Refactoring|nopanel=true}
{excerpt-include:TC X9 Interface Flexibility (Xmapper replacement)|nopanel=true}
{excerpt-include:TC 1.0 CS Support JIRA Uplift - P1|nopanel=true}
{excerpt-include:TC 1.0 CS Support JIRA Uplift - P2|nopanel=true}
{excerpt-include:TC 1.0 Branch Volume Improvements|nopanel=true}
{excerpt-include:TC 1.0 CS SCERs Uplift|nopanel=true}
{chart}
On each child pages below is the code....e.g.TC 1.0 CS Support JIRA Uplift - P1
{excerpt}
{table-plus:id=CSSupportJIRAUpliftP1Planned|columnTypes=S,-,.|autoNumber=true}
|| Plan || Start|| End|| Percent\\Complete||
|TC 1.0 CS Support JIRA Uplift - P1| 02/06/2014| 03/10/2014| 100% |
{table-plus}
{excerpt}
Any help would be appreciated! Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
My current version of Confluence didn't like the CSV macros in Bob's original answer. I was able to get it working by pasting the below into the page as 'confluence wiki markup':
{chart:type=gantt|dataOrientation=vertical|columns=,,1,2,3,4|displayData=before|width=500|dateFormat=MM/dd/yyyy}
|| Plan || Start || End || Percent\\complete ||
|| Create issue | 1/30/2007 | 2/1/2007 | 30%
|| Provide examples | 1/30/2007 | 2/7/2007 | 40%
|| Write code/tests | 2/3/2007 | 2/4/2007
|| Write docs | 2/4/2007 | 2/5/2007
|| Release update | 2/5/2007 | 2/5/2007
|| Actual || Start || End || Percent\\complete ||
|| Create issue | 1/30/2007 | 2/11/2007 | 100% |
|| Provide examples | 1/30/2007 | 2/17/2007 | 90% |
|| Write code/tests | 2/3/2007 | 2/14/2007 |
|| Write docs | 2/4/2007 | 2/15/2007 |
|| Release update | 2/5/2007 | 2/15/2007 |
{chart}
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Aaron,
Did you have to do anything special to get this to work. I've tried what you have above as well as an example in the Atlassian documentation and all it does is display, "No Data Available".
I've copied and pasted your example above and I've created an empty chart macro just '{chart:type=gantt|dataOrientation=vertical|columns=,,1,2,3,4|displayData=before|width=500|dateFormat=MM/dd/yyyy}' and then pasted the data into it but I get the same thing - "No Data Available"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As an alternative you can cretae Gantt chart using Chart from Table macro (Table Filter and Charts macro).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi everyone,
Gantt Chart Planner for Confluence is an option to create Gantt charts in confluence.
And, an article Plan Projects and Roadmaps with Gantt Charts in Confluence Cloud summarizes the pros and cons of various ways to draw Gantt charts in Confluence Cloud. I think it helps you select your best way to draw Gantt charts.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi everyone,
As an alternative if you are looking for advanced but easy to use gantt charts in Confluence, please try out our add-on: Easy Gantt Charts for Confluence
You can make gantt charts by entering table data and using drag & drop features. Let us know if you face any issues.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Has anyone ever got the chart macro actually pulling data from JIRA using a JIRA filter and displaying in the Gantt or am I just trying in vane...........
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Confluence native Chart macro doesn't work with Jira Issues macro, but Chart from Table macro (Table Filter and Charts macro) does.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks, so I am pissing in the wind.
Another plug in to buy..........great.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I've tried to put a jira filter on the page so I can copy the data into a table on the chart. I'd love to hide the jira filter - is there anyway to do that so I just get the gantt chart?
(I also don't want to buy another add on).
Thanks!
Laurie