Dear Community, I am facing one challenge regarding waterfall projects dashboards creation in Jira for which i need help.
Use Case:
We have Major 5 Phases of a waterfall Project.
1. Planning
2. Initiation
3. Execution
4. Monitoring and Control
5. Project Closure
For Planning phase i have 4 Main Tasks which for which i need to track progress same like other phases.
Issue which I am Facing:
I want to make dashboard which show me the progress of each phase as per below:
Phase | To Do | In Progress | Done | %Age |
1. Planning | 1 | 2 | 1 | 33% |
2. Initiation | 0% | |||
3. Execution | 0% | |||
4. Monitoring and Control | 0% | |||
5. Project Closure | 0% |
Need support from community to solve my problem or suggest the best approach which i should follow to get my required results.
Welcome to the community!
Why dont you try using the Two dimensional filter Gadget to achieve your usecase?
Just want to get more detail.
I have 34 Tasks and 5 Main Phases like each phase of project is distributed among multiple tasks. Just like i mentioned in table.
Planning phase contains 4 Tasks. My question is where we can define project phase and tasks progress for different phases as well.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.