Is there a way to prevent the status of the parent issue from being done if the status of all child issues is not in the done state?

1 answer

1 accepted

0 votes
Answer accepted
Naveen Kumar_Appfire
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 1, 2023

Hi @koutarou ishibashi

We suggest you use the JMWE app to achieve the use case you are looking for

https://marketplace.atlassian.com/apps/292/jira-misc-workflow-extensions-jmwe?hosting=cloud&tab=overview.

After installing the JMWE use the below validator to achieve the same

  • Linked Issues Status Validator (JMWE app)

Refer to this article for configuring the Validator https://appfire.atlassian.net/l/cp/At9pX2Dk