If Task A duration changed, how task B/C automatic change by dependency

Jitendra Kumar Maurya
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 24, 2022

Task A schedule 6/1-6/10

Task B will start from A finished, its schedule is 6/11-6/20

Task C will start from B finished, its schedule is 6/21-6/30

If Task A postponed 6/1-6/15

Task B could auto changed 6/15-6/25

Task C could auto change   6/26-7/5

How to make the "auto change" happen?

2 answers

0 votes
Robert Keiper _K15t_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 28, 2022

Hey @Jitendra Kumar Maurya 

you might want to check out my company's app Orderly Databases

Although it won't solve your actual request for automatic date changes by dependancy, with Orderly you will be able to:

  1. Change Date-fields in Database tables on the fly without having to open the editor;
  2. Reference a Database table on other confluence pages. So even if you need to change dates manually, you would only need to do it once.

Cheers,
Robert

0 votes
Fabian Lim
Community Champion
February 26, 2022

Hi @Jitendra Kumar Maurya

Welcome to the community!

Can you provide more context on which macro or plugin you are using? 

Regards

Jitendra Kumar Maurya
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 27, 2022

I am using date macro, my do is if I change one date in table others row date's should change automatically 