Hi @Rob Staples,
Pretty sure that the way this is implemented is by using two Task Report macros with the same filter. Additionally, the first macro is set up to only show incomplete tasks, while the second macro is set up to only show complete tasks. This should "move your tasks down" to the second macro once you complete them. Hope this makes sense! :)
Cheers,
Sven from Lively Apps - Makers of Task Reminder for Confluence
@Sven Schatter _Lively Apps_ @Thanks for your response.
It makes sense but I don’t know how to add the ‘task complete’ status column with a macro?
also, the actions would be documented on other pages for example, I manage different projects using separate reports - the actions need to be pulled from the notes made on those pages and populated in this one central log?
Any help is greatly appreciated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Rob Staples,
Not sure whether you're on Server or Cloud but you need to insert the Task Report macro into your page. Like this:
When you do that, a dialog should open up where you can choose the settings for the settings for the macro. So in your cases, you want to look for the "status" option:
Hope this helps!
By the way, if you have any other ideas how you want to use Confluence tasks, let me know! We are always looking for cool ideas to improve our app Task Reminder for Confluence. :)
Cheers,
Sven
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sorry, just saw that you had a second question! The Task Report macro also allows you to filter for tasks that are on a given page. So you can decide exactly what tasks will be displayed. I think this is exactly what you want:
There's even more filtering options in the macro. Definitely have a look at it, I think it can do exactly what you need. :)
Cheers,
Sven
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Sven Schatter _Lively Apps_ great, thks vm!
It would be good if 1) update comments could be added to task on the task report and 2) the task status could be updated on the task report page
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.