Task Report - Specific tasks per project and list them on the project page

Tobias Wagner June 17, 2025

Hey there,

in confluence we have single pages for all our projects. During our meetings we open a new page for the meeting notes and start writing tasks due to the projects. Our plan is to write all the tasks for different projects in the meeting note page (one page per meeting) and let confluence show the project specific tasks on the right project page.

Example:
Meeting notes

[] write report for project a

[] call customer for project b

[] sell product project c

 

Page of Project a

[] write report

 

Page of Project b

etc.

 

We already tried the task report makro, but that does not fullfill the task. It can only show all the task of one page and not filter the page and filter the task for the right project.
Does anybody have a solution for this?

3 answers

0 votes
Florian Schneider June 19, 2025

Hey @Tobias Wagner ,

do you use Jira in your organization? With Jira you have more filter options. Maybe there is a way to use the app "Viable Issues" to create tasks fast and consistently the right tasks and use the filter macro to search/show it on the right Confluence page.

Is there a way? We can definitely discuss this together if you'd like.

Tobias Wagner June 19, 2025

Hey @Florian Schneider

 

thanks for your answer. As I discovered today we already had the automation rules, but I could not see them, because I had no admin access. So now I could start building our own automation rule for that, but for that I could need some help as well.

Florian Schneider June 19, 2025

Hi @Tobias Wagner ,

I am not the automation expert, but I can try to help you. If you´d like it, we can make a short call and I will invest 30 minutes to find a way for your automation rule. Is that okay for you?

If yes, you can contact me via LinkedIn https://www.linkedin.com/in/florian-schneider-workplace/ 

Tobias Wagner June 19, 2025

Hey @Florian Schneider

 

thx for your offer. I worked my way through the automation yesterday and realised that unfortunately it doesn't work the way we want it to. Obviously we would need jira to solve our problem, because in confluence you can't set individual tags (so one for each task on the same page), only entire pages can be labelled.

Like Florian Schneider likes this
0 votes
Staffan Redelius
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 17, 2025

Hi @Tobias Wagner and welcome to the Community

What is it that you are lacking when it comes to the task report?

  1. Create a Team via the ...More menu in the left bar for each project.
  2. In the meeting notes do a @mention of the team for each task (/action + @mention team) Confluence will automatically add the name of users in the team.
  3.  On each Team page use the Task report-macro and filter items related to users in the team under "Assigned to". 

Optionally you could add a specific label (i.e "project_actions") for the this type of meeting notes to be used in the task report to distingush these actions from other actions on other pages. 

 

Tobias Wagner June 17, 2025

Hey @Staffan Redelius and thank you
The problem is that I cant assign one task to one project - if there are many task for different projects on one meeting note page. I can only assign a task to a person, not a project.
I tried to create a team like you mentioned. But there is no option for me when clicking the ... next to the project in the left bar. There is only Editing, Rename, Marking, Copy Link, Moving, Automate, Archiving and Delete.

Tobias Wagner June 17, 2025

Okay, I found the option. This is not suitable for us, because one team has several projects. We want to have a "messy meeting note" with all information we discussed in that meeting and all the tasks we created in there. The macro then should display the, for the project itself, specific tasks on its already existing project page.

Staffan Redelius
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 17, 2025

Could you share a print screen of your sidebar in Confluence? It should look like this if you are on the new layout

 

Skärmbild 2025-06-17 143955.png

Tobias Wagner June 17, 2025

Screenshot 2025-06-17 152200.png
german version

0 votes
Nikola Perisic
Community Champion
June 17, 2025

Welcome @Tobias Wagner 

Have you tried the automation rules with the action to write the content to the correct project page?

Tobias Wagner June 17, 2025

Is there any tutorial you can show me?

Nikola Perisic
Community Champion
June 17, 2025
Tobias Wagner June 17, 2025

Thank you very much. Seems like our company has no license to use the automation rules etc. Any other solution with the "normal macros" or so?

Nikola Perisic
Community Champion
June 17, 2025

Normal macros - the closest one was the one you have mentioned, the other third party apps I can think of is ScriptRunner. It is a paid app, but it has the option for automation.