Hi all,
4 teams are 4 separate scrum boards and so, 4 velocity charts in jira. I want to show all these 4 charts in confluence dynamically. How we can do that?
1) If any velocity chart is added with new sprint data, then confluence graph should be automatically updated,
You can use "Great Gadgets for Jira" by StonikByte. It works well but if you have too many Gadgets on the same page, you can get loading issues.
Thanks @Ditte Simard for mentioning our app as a potential solution.
Indeed, with our Great Gadgets app you can display a chart for each team in both Jira and Confluence. If you have Jira Server / Data Center, you can import the gadgets in Confluence.
Not sure what loading issues is @Ditte Simard referring to. We are willing to assist as necessary. Just contact us over email at support@stonikbyte.com if you have any questions.
Thank you,
Danut M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks @Danut M _StonikByte_ I will definitely reach out!
Performance is great when I use the widgets in the Jira but I have noticed loading problems if I have more than 3 graphs on one Confluence Page. I would love to trouble-shoot this with your team.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.