Team Calendar showing additional Color/Bar on Right of Event

Brian Taylor
Contributor
May 6, 2019

Recently we have notice that there is an additional Color/Bar on right of events in Team Calendars that is confusing some users as to the type of event being entered.

 

Screen Shot 2019-05-06 at 12.49.40 PM.png

1 answer

0 votes
Diego
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 8, 2019

Hello there Brian!

As I understand, there is now a small colored overlay on the events. Is that correct?

I tried to replicate this behaviour but was ultimately unable to. I inserted every type of event my calendar had but none of them showed this overlay:

Screen Shot 2019-05-08 at 10.30.37.png

With this in mind, could you clarify a few points for us? Here they are:

  1. Is this visible in all types of events?
  2. Was Team Calendars updated prior to this issue?
  3. Is this color overlay present in any browser?
  4. Is this present for all users?
  5. Have already existing events been affected?
  6. Is this present in all newly created events?
  7. Is this present in all events created by any user?

Looking forward to your reply Brian!

Brian Taylor
Contributor
May 8, 2019

 

  • Is this visible in all types of events?
    • Yes visible in all event types
  • Was Team Calendars updated prior to this issue? 
    • This happens on existing and new Calendars 
  • Is this color overlay present in any browser?
    • I have tried Chrome, Firefox, IE and Safari and still happens 
      in two environment our development and production instances 
  • Is this present for all users?
    • yes appears fro all users 
  • Have already existing events been affected?
    • Yes appears fro existing and new events 
  • Is this present in all newly created events?
    • Yes existing and newly created issues 
  • Is this present in all events created by any user?
    • Yes existing calendars and newly created calendars

The timing appears to have happened when we upgraded to 6.15.2 according to users they did not notice this issue until after the upgrade. 