Platform Terminology Setup: Release = Planning Interval

YY Brother
Community Champion
February 5, 2025

Hi,

According to Develop on Cadence & Release on Demand  in SAFe 6.x, it seems that Planning Interval is not the same thing as Release. How do you think of it?

Thanks,

YY Brother

1 answer

0 votes
ahmet_kilic_catworkx_com February 5, 2025

No it is not:

Planning Interval is just a cadence-based timebox, typically 10-12 weeks.

Release is batch in any size of work teams deliver.

 

Since you're asking the question in Jira Align community, I would emphasize the point that Jira Align fits very well to this and further approaches regarding release delivery.

 

I hope this helps.

Best wishes,

Ahmet Kilic 

Enterprise Agility Consultant @ catworkx

YY Brother
Community Champion
February 5, 2025

Thanks Ahmet. Then Jira Align product team needs to modify it.