We've implemented the JIRA <--> JIRA Align interface for several (approx. 50) teams but I've got some that I'm not able to reliably integrate and I'm looking for tips / guidance on how to best troubleshoot these situations.
Completed:
Problems:
What are the suggested steps for continuing to investigate these issues?
I suggest forcing a sync from Jira to Jira Align. Add a label to the problem stories/issues in Jira, save, wait a few mins. I recommend deciding on creating 2 labels: Admin_Sync_to_Align and Admin_Sync_to_Jira for consistent future use, but really any label will do.
Also, if you haven't run the project/board integration yet, now would be a great time to do that. Go to Jira Settings, Jira Integration, and add the Project, Board, and a JQL: labels= Admin_Sync_to_Align
Another thing to check is your state mapping on the project in question. In Jira Settings, Projects. Under process step mappings, be sure the toggle is green, choose your Work Item Type, and then choose preload and update. If preload and update does not work, it means you have problems in your mapping.
Also, check your Jira Board column mappings. If there is a story with a status in the unmapped column, it will not sync to JA. Map the status to the columns and see if that fixes it.
Are the problematic issues coming from different Jira Projects then the Projects that contain the Stories? One way to check is looking at the issue key (STORY-1 vs SPIKE-3). If so, validate that those other Projects are mapped to Jira Align.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.