Hi @Arunkumar Ponnuraju ,
I am able to replicate the visibility / UI-UX experience you shared, and believe it's simply a JPD limitation with the timeline view at the moment.
Since the "scale" of the view is set to quarterly, the idea is placed in the general quarter (July-Sept) as a whole at both start and end of the quarter - instead of being placed on the actual date(s) based on the JPD date-fields.
It also happens when the "scale" is set to monthly:
I believe engineering is working on enhancing the timeline's visibility, but no firm ETA on when this will be available. I will relay the information to our teams internally. Feel free to also share this with them under the Give feedback tab.
This will create an internal ticket with the engineering and product teams which they are reviewing regularly to improve JPD.
Hi @Nick Haller ,
Just wondering from your end if there is any update on the internal ticket that was created last year? It makes it difficult to promote jpd in my organization when we can't use a timeline view. Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi @Arunkumar Ponnuraju , we've turned on the new experience for you that supports finer granularity. If you refresh your screen it should now support monthly granularity. Does it work?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi @Tanguy Crusson thank you.
But seems not working, still same as originally reported.
Can you confirm the new experience Is applied to https://akpppds.atlassian.net/?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
is the timeline still looking exactly like the screenshot you shared ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Now i see that its applied. And seems better than earlier. Thank you again!
Though understnad that at big picture its not critical. But when we show this view to our higher ups, they get sort of confused u said the project will start on 15th, but here its at the begining of the month, and we waste time explaining the same... 15days is lot in that sense.
In that sense still would prefer that timeline reflects the actual date selected.
If you could consider to add to it will be great.
For the moment i will try manage with it. When u have any updates please let me know.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Will there be an update to reflect the actual date in JPD or have day time scale? Timeline still rounds it to the nearest mid or end of the month. I can create a marker for a date for releases of our ideas, but can't get the ideas to line up to that date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.