Freyr Gudmundson June 26, 2025

I have connected some ideas in JPD to projects in Atlas. I can get the target date to correctly update from Atlas, however, it seems that I cannot do the same for start date, see image. Is that by design?

at.png

1 answer

1 accepted

3 votes
Answer accepted
Tanguy Crusson
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 26, 2025

Hi @Freyr Gudmundson I wouldn't say that's "by design" but it's a current limitation - we need to add support for the project start date, it only supports target dates today.

Freyr Gudmundson June 26, 2025

Thanks!

Just a quick thought, it was confusing to be able to choose the same field for both start and end from atlassian. I didn't notice first that it was the same field, so when JPD showed me the project visually I couldn't figure out what went wrong. Feels like the UX should not allow me to choose the same field there, or at least warn me.

Also, I couldn't find documentation about this limitation.