2nd SCRUM Board in the same Project doesn't show the same Sprints

Mireille
Contributor
October 24, 2023

Hello,

I had 1 scrum board with current Sprint and 4 additional ones.

I created a second scrum board, in that new board, I see the current sprint and one more but not the last 3, so I created one that had the same name and date, but I can see that the Sprint number is different.

 

The second scrum board doesn't show all the epics, how can both board for the same project share the same sprints

Thank you

1 answer

1 accepted

1 vote
Answer accepted
Mikael Sandberg
Community Champion
October 24, 2023

This is expected. Sprints that are created in one board will only be visible in other boards if those boards shows issues that have been linked to the sprints in the first board.

So in your example it means that on the second board you are seeing the current sprint and the other one because you have issues on that second board that is linked to those sprints.

Mireille
Contributor
October 27, 2023

Indeed, thank you so much! sorry for the delayed answered. I did add stories and the sprints appeared :)

Like Mikael Sandberg likes this