About some issue state and kanban board sprint question

mj
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 4, 2020

1. why the issue status is Done ,but still appear the Backlog list?

2. How to creat the Sprint in a  project. My project only have Kanban Board and Reports.

    There is no Sprint.

1 answer

0 votes
Warren
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 5, 2020

Hi @mj 

  1. Is this something new or has it always done that? You may need to look at your workflow because generally, with a Kanban board, only items in the Backlog status will still show in the Backlog.
  2. You cannot create a sprint from a Kanban board. If you want to work with a sprint, you will need to create another board and create it as a Scrum board. This new board will then allow you to create a sprint

Suggest an answer