Quick question:
We have a board which has 2 projects link into it. BUT even thought the used have permission to start and stop sprint only one Sprint can be started? Any idea how to fix?
Hi @Sian Snook
Maybe the parallel sprints feature will be helpful? This feature allows you to run multiple sprints at the same time :)
You can turn it on under Settings > Products > Parallel sprints
More about it: https://support.atlassian.com/jira-software-cloud/docs/use-parallel-sprints/
Kind Regards,
Weronika
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hey @Sian Snook
Only one active sprint is allowed per board by default in Jira. To start multiple sprints, you need to enable the Parallel Sprints feature in Jira settings (requires admin access). Also, ensure sprints are created on project-specific boards and users have the correct sprint permissions in all linked projects. Let me know if you need help with the setup!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.