Katie Scholl February 3, 2022

Hi all, I am new the Jira Advanced Roapmaps and have been watching some Atlassian youtube videos. On the videos, the examples have an option to adjust the timeline range in the top right with options such as 3M, 1Y, Custom, etc. My advanced roadmap does not show me this option? Am I doing something wrong or has their been an update and this is now in a new location? Thanks in advance! 

This is what the top right looks like for me: 

2022-02-03_13-50-56.png

 

This is the top right from a tutorial video on Atlassian's youtube channel.

2022-02-03_13-50-33.png

1 answer

1 accepted

0 votes
Answer accepted
Sara Hekmat
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 3, 2022

Hi Katie,

You can find the date-range options in the bottom-right of the plan timeline. The location has been changed in the new version. 

Regards

Sara

Screen Shot 2022-02-04 at 9.09.06 am.png

Garrett N_ DeSantis
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 5, 2022

I notice the custom range is simply setting a start and end date to the x axis. When will we be able to see/edit tasks on an hour/half hour basis via advanced roadmaps? Advance roadmaps doesn't adequately meet our needs otherwise.