Hey there,
On a project level, the roll up dates are correctly showing. I created a view of all initiatives across all projects and the roll up dates are not updating there.
What can I do? (Two examples attached)
Project = shows accurate rolled up dates
ORG= Roadmap I created cross org that is not showing rolled up dates
THANKS!
As you can see in your first screenshot, the rolled up date you see there is displayed in italic. That means it is a calculated value you see on screen. It is not persisted in the Jira database and it is calculated dynamically based on the child issues you (don't) see listed under the > levels of the parent.
In your second screenshot, those child issues are not included in your selection. And so the tool does not have any data available to roll up into the parent level. That's why the date is not showing in your second example.
Hope this clarifies!
HI! Thanks for the response! I actually figured it out. Since the roll up dates are using the team's scrum board, I had to add that as an issue source.
Now my next question, we have Kanban teams. Since they won't have scrum boards, what can I do for their roll up dates?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.