Roll-Up dates is a great feature, that I am using and needing a lot. Today I found out, that the Roll-Up Dates however are not working in the read-only view.
E.g. I embedded the Plan on Confluence. It will not correctly display my timeline, because the roll-up dates are missing. Do you have any ideas?
Hi @Alexander Wirtz welcome to the Atlassian Community!
Do you see the roll-up dates for a user with only Viewer permission in the Advanced Roadmaps plan directly?
Hey @Dave Mathijs ,
user with only viewer permissions can see the roll-up dates. So it seems that something is wrong with the "share as" function.
I just also tested the simple link share option and the same error appeared.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.