I have imported my team's information multiple times, excluding certain things each time. But no matter what I do, the sprint dates are ALWAYS wrong. Each sprint has set dates in JIRA but those don't get brought into my plan. They are a few days removed and never evenly.
Hi @Jaclyn Fine,
If you are on a self-hosted environment (server), it could be interesting to know what's the largest difference between your JIRA date and Portfolio date. If it's always either the same or a day difference then I'd advise checking your database, server instance and JIRA user timezone configuration.
If you are on a Cloud offering you could check the plan timezone configuration to ensure it matches your expectation (see Configuring working hours and days) and if that doesn't work then contacting support would be the way to go.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.