An option to see all active sprint data (start/end date)

Sergiy Nikolaevskiy June 18, 2018

Is there an option in Jira to see start/end sprint date for all projects, as a spreadsheet or so? The main idea is to have this info in one place

1 answer

0 votes
João Nunes
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 19, 2018

Hi, Sergiy. How are you today?

I'm afraid that won't be possible because, due to the application design, there is no native way to change that option on Jira right now. However, I've opened this feature request which aims to make that possible. We strongly recommend you to access that feature request page, click on vote for that to increase its relevance and click on Start watching this issue to receive all the updates about that. Also, we would appreciate your feedback on that feature, you can do this by leaving a comment on the ticket, this helps us prioritize and understand the use case of the feature request.

If you are not familiar with our Feature Request Policy, you can learn more about it here.

As an alternative for that, we can use a third-party add-on like All-In-One Reports for Jira. This add-on have a 30 days free trial for both Jira Cloud and Server.

After installing the add-on, please follow the step-by-step procedure below:

  1.  Click on AIO Reports at the menu bar > on the add search field, type Sprint.
  2. Select the Sprint Name, Sprint Start Date, and Sprint End Date.

Let me know if that helped you :)

Kind regards,
JOÃO NUNES
Jira Support Team