Are there any visual indicators that differentiate Due Date and Target Date in advanced roadmaps

Neil Wills
Contributor
May 10, 2022

Are there ant visual indicators that differentiate Due Date and Target Date in advanced roadmaps.

 

I note that due date will change the length of the gannt chart.

1 answer

0 votes
Mykenna Cepek
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 10, 2022

If I remember correctly, you can configure one or the other as a global setting for all the advanced roadmaps in your instance - either Due Date OR Target End.

Likewise, you can specify one field to represent the starting date.

The documentation is sparse on the topic:  Use custom dates in Advanced Roadmaps

If others are using advanced roadmaps, and you change this configuration, it may substantially impact how their roadmaps appear. You can use various methods (e.g. automation) to migrate data between the various date fields, if necessary.