I need to capture the fields "Original Estimate" and "Remaining Estimate".  When and where is the data entered?

 

Thanks

2 answers

0 votes
Aron Gombas _Midori_
Community Champion
January 24, 2018

As those two fields are standard Jira fields, their changes (when? who? old- and new value) are listed in the Change History view of the corresponding issue.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 23, 2018

They're stored as part of the "time tracking" field.  As for "when", it's when the users enter related data.  Could be an original estimate entered on creation, or later.  Remaining estimates are affected by people logging work, or changing it directly.

I'm not sure what you are looking for when you say "capture"